BLD-2026-0129 Kitting
250 × PP8FR — Power Port 8FR — fire tripped power distribution module · rev C
Cannot be kitted — short of 2 components
Every shortfall is covered by stock already paid for and on the water. The first of it lands 15 Aug 2026 — 2 days ago.
Planned
Kitting
On the bench
Test & QA
Complete
Kit list
9 component lines against the shelf at Hawker. $16,365 of material at standard cost.
| Ref | Component | Description | Needs | Issued | On shelf | Short | Cover |
|---|---|---|---|---|---|---|---|
| — | PCA-PP8 | PP8 main board, populated | 250 | — | 18 | 232 | 900 on the water · 23/08 |
| — | ENC-PP-ABS | Enclosure — Power Port ABS base and lid | 250 | — | 39 | 211 | 1,800 on the water · 15/08 |
| — | DIN-CLIP | DIN rail clip — 35mm, screw fixed | 500 | — | 3,931 | — | On the shelf |
| — | LBL-PP | Label set — Power Port, output legend | 250 | — | 2,143 | — | On the shelf |
| — | TB-PLUG-2P | Plug — 2 pole mating half | 2,000 | — | 9,531 | — | On the shelf |
| — | TB-PLUG-3P | Plug — 3 pole mating half | 250 | — | 3,726 | — | On the shelf |
| — | FUSE-1A | Fuse — 1A 5×20mm slow blow | 500 | — | 7,350 | — | On the shelf |
| — | BOX-RETAIL | Retail box and insert — printed | 250 | — | 2,658 | — | On the shelf |
| — | SCR-M3-8 | Screw — M3×8 pan head, black | 1,000 | — | 48,015 | — | On the shelf |
Build order
- Quantity
- 250
- Raised
- 13 Aug 2026
- Due
- 24 Aug 2026 in 7 days
- Owner
- Ken Mckeon
- Bench time
- 75 h 0 m
- Material at standard
- $16,365
- Finished value
- $22,890
Waiting on
PCA-PP8 232 short
900 on the water, landing 23 Aug 2026
ENC-PP-ABS 211 short
1,800 on the water, landing 15 Aug 2026