DSN-2026-01 Prototype

Safety Call Point — flush variant

Where it is up to
Open 5 months · target 2 Oct 2026
Concept
Design
Prototype
Pilot run
Released
Architectural fit-out demand from CSD and Hills. Front plate tooling quoted by Meiyu, awaiting sample approval.
Tasks
1 of 5 done. Drag a card between columns.
Open 2
Field trial with CSD Mulgrave
Ken Mckeon 14 Sep
Datasheet draft
Ken Mckeon 7 Nov
Doing 2
Sample approval — colour and legend
Ken Mckeon 22 Oct
Assemble ten prototypes
Ken Mckeon 21 Sep
Done 1
Front plate tooling quote — Meiyu
Ken Mckeon 9 Aug
Documents on SCP-F
Product hub →
KindTitleRevUpdatedBy
Data Sheet SCP-F Data Sheet draft 12 Dec Ken Mckeon
Install Note SCP-F Installation Note draft 12 May Dan Whitlock
Quick Install Note SCP-F Quick Install Note draft 22 Oct Ken Mckeon
Application Note SCP-F — upgrades and retrofit application draft 9 Nov Dan Whitlock
Photo SCP-F product photography — front, angle, installed draft 28 Mar Dan Whitlock
Project
Owner
Ken Mckeon
Range
Safety Call Point
Opened
1 Apr 2026
Target release
2 Oct 2026 in 46 days
Part code
SCP-F
Lifecycle
In design
Spend
$28,400 of $42,000
67.6% of budget committed