Where it is up to
Open 1 months · target 1 Mar 2027
Concept
Design
Prototype
Pilot run
Released
Asked for by two integrators via Seadan. Same shell, different board — worth doing if the FAST termination volume holds.
Tasks
0 of 2 done. Drag a card between columns.
Open 1
Ask Seadan for indicative annual quantity
Ken Mckeon 18 Oct
Doing 1
Scope the variant against the FAST termination volumes
Ken Mckeon 26 Sep
Done 0
Nothing here
Project
Owner
Ken Mckeon
Range
ATMOD
Opened
14 Jul 2026
Target release
1 Mar 2027 in 196 days
Spend
$820 of $12,000
6.8% of budget committed
Tasks done 0 / 2