← Build orders
BLD-2026-0136 Planned
150 × PP5FR-UNI — Power Port 5FR-UNI — versatile power distribution module · rev C
Cannot be kitted — short of 1 component
Every shortfall is covered by stock already paid for and on the water. The first of it lands 15 Aug 2026 — 2 days ago.
Planned
Kitting
On the bench
Test & QA
Complete
Kit list
8 component lines against the shelf at Hawker. $8,085 of material at standard cost.
| Ref | Component | Description | Needs | Issued | On shelf | Short | Cover |
|---|---|---|---|---|---|---|---|
| — | PCA-PP5 | PP5 main board, populated | 150 | — | 209 | — | On the shelf |
| — | ENC-PP-ABS | Enclosure — Power Port ABS base and lid | 150 | — | 39 | 111 | 1,800 on the water · 15/08 |
| — | DIN-CLIP | DIN rail clip — 35mm, screw fixed | 300 | — | 3,931 | — | On the shelf |
| — | LBL-PP | Label set — Power Port, output legend | 150 | — | 2,143 | — | On the shelf |
| — | TB-PLUG-2P | Plug — 2 pole mating half | 750 | — | 9,531 | — | On the shelf |
| — | TB-PLUG-3P | Plug — 3 pole mating half | 150 | — | 3,726 | — | On the shelf |
| — | BOX-RETAIL | Retail box and insert — printed | 150 | — | 2,658 | — | On the shelf |
| — | SCR-M3-8 | Screw — M3×8 pan head, black | 600 | — | 48,015 | — | On the shelf |
Build order
- Quantity
- 150
- Raised
- 16 Aug 2026
- Due
- 1 Sep 2026 in 15 days
- Owner
- Ken Mckeon
- Bench time
- 38 h 30 m
- Material at standard
- $8,085
- Finished value
- $11,348
Waiting on
ENC-PP-ABS 111 short
1,800 on the water, landing 15 Aug 2026